Assumptions in the Shirokuma case
Here are some interesting questions in the Shirokuma case, which highlight the difficulty of preparing estimates in the absence of hard information.
The engineer in the case study may have been thinking that a certain number of individuals would collectively spend 6 months on the development. For the purposes of the exercise you may assume a team of three people. Doubling the size of the team might at best reduce this to three or four months, and gains beyond that are unlikely - at least for this project.
- The durations of certain tasks in the project have only length in time rather than person-months? does that mean that those taks require the work of the whole group or should we consider the duration units as person-months/weeks? For example, the most problematic so far has been the six months required by the DSG for develpment kits, has that got to be considered as 6 months for the whole group or can it be considered as 1 month if the tasks is undertaken by 6 engineers?
The engineer in the case study may have been thinking that a certain number of individuals would collectively spend 6 months on the development. For the purposes of the exercise you may assume a team of three people. Doubling the size of the team might at best reduce this to three or four months, and gains beyond that are unlikely - at least for this project.
- Also, there is no mention of the price of bought in power supplies; which come optionally to making them ourselves, so should we consider buying them in as an unconsiderable option?
- Thirdly, The marketing staff have no salary guideline, so should we guestimate one? and are we required to include healthcare, pension costs etc... on top of the stated pay (usually doubles it, more or less).